BHANUPALLI -BILASPUR- BERI RAILWAY LINE (63.5 Km) IN LENGTH DELAYED BECAUSE OF THE FULFILLMENT OF COMMITMENTS AND REQUIRED LAND ACQUISITION.

RTI issue had been raised with regard to construction of Bhanupalli -Bilaspur-Beri 63.5 KM length of the railway line with the department of Railway division working for the speedy construction and approval as well as implementation of the project orientation scheme continued since long , however the central government blaming for the cost sharing money to state government of Himachal pradesh. The work has been taken in hand for which 79.57 hectare land out of the total land required for the project 124.02 hectare in Himachal pradesh has been acquired and the work is taken in hand and for which an expenditure of rupee 5205 crore has been incurred on this railway project but rupees 1351 crore is outstanding with the state government of Himachal pradesh. The second railway line